P
ENI EI-39Eugene Island 39 Decommissioning
Pre-mob · Mobilization Jun 25 · Contract 5010006273
BK

Mobilization readiness

What's blocking Jun 25 — pre-mob only
Tender HandoverBehind
83%done· target 95%
Early Key DeliverablesBehind
45%done· target 100%
PM & Admin
32%done· target 35%
HR
15%done· target 15%
HSEQRBehind
19%done· target 52%
Finance
16%done· target 16%
Engineering
5%done· target 5%
SCM / Procurement
2%done· target 2%
Operations
1%done· target 1%
Filled bar = actual progress · Tick = target % for today. Retires once offshore.

Execution & milestone timeline

Work completes → milestone bills → cash unlocks
May → Nov · 14 phases
May
Jun
Jul
Aug
Sep
Oct
Nov
PM&E (onshore)
30d
$320K
$192K
$128K
Mobilization
Well #2 — diagnostics & P&A
$1127K
Well A001 — P&A
$488K
Well A002 — P&A
17d
$1721K
Well A003 — P&A
17d
$1653K
Well A004 — P&A
$1078K
Pipeline PSN 12515
$249K
Pipeline PSN 12507
$304K
Platforms — cutting & removal
19d
$1045K
$3225K
Disposal
Site clearance
Transit & demob
Closeout (PM&E)
30d
Today · Jun 4
PM&E
Mobilize
Wells
Pipelines
Platforms
Closeout
|
Billed
Upcoming
Planned

2-week look-ahead

Jun 4 → Jun 18
  • PM&E permit package targeting Jun 20 — triggers 30% billing on Milestone 1.1.
  • Tier-1 vessel mob window Jun 25 — standby exposure if window slips.
  • HSE bridging document review with Eni HSEQ (this week).
  • Final APM submissions to BSEE pre-mob.