ENI EI-39Eugene Island 39 Decommissioning
Pre-mob · Mobilization Jun 25 · Contract 5010006273
BK
Contract value
$11.97M
Lump-sum
Current phase
Mobilization
PM&E in progress
Offshore window
Jun 25 – Oct 7
2026
Overall status
On track
To mobilize Jun 25
Safety TRIR
0.00
0 recordables

Needs attention

AI agents continuously scan bids, master sheet, DPRs, email & calls — surfacing what to act on
4 system·4 open·2 done
  • Margin has no single source of recordClient bid $11.97M vs internal build $12.95M (−$981K); 5% markup → ~4.8% GPM; facilities vs Morrison −3%.
    Steve L / Danny
  • HSEQR readiness behind plan19% complete vs 52% expected, against Eni's heavy HSE/permitting requirements.
    Hannah
  • DPR in project folder belongs to a different blockDE25060 daily report references WD 28/29 & GI-22, not EI-39 (lease G15239) — excluded from EI-39 actuals.
    Kaylee
  • Master revision to confirmRev B vs Rev C both carry $11,972,356; confirm authoritative.
    Steve L
  • Submit 50% of Milestone-1 invoicePM&E 50% billing — confirm with finance and send today.
    6/3
    Kaylee
    confirmed
  • Lock Tier-1 vessel mob window (Jun 25 standby)Standby fee exposure if window slips. Confirm with vendor.
    6/2
    Steve L
  • Walk Eni through HSE bridging documentEni HSEQ requested a working session before mob.
    Hannah
  • Confirm permit-package owner for 30% triggerPM&E 30% milestone depends on package handoff.
    6/3
    Steve L / Parker
HighMediumLow· grouped by source, sorted by priority within each lane

Field

Coordinate-accurate schematic · Eugene Island Block 39A
PSN 12515 · 4"PSN 12507 · 8"SSTI tie-inoff-platformAEI-39 A#4#2EI-39 #2N≈ 0.25 nmPlatformCaissonPipelinePABN
Eugene Island Block 39A · Gulf of Mexico · 10–17 ft water depth
Field assets
  • EI-39 A
    4-pile facility · Sep 21–26
  • EI-39 #2
    Caisson · Sep 15–19
  • EI-39 #4
    Caisson · Sep 19–20
  • PSN 12515
    4" · #2 → A · Aug 25–26
  • PSN 12507
    8" · A → SSTI · Aug 26–28
Hover a node to see details. Coordinates from contract master sheet.

Delivery

Execution excellence, evidenced
Schedule
On track
Mobilize Jun 25
Next milestone
PM&E permit pkg
targeted Jun 20
Forecast completion
Oct 2026
Closeout Nov 6
Milestones delivered
0 of 12
Begins offshore
First-time-right
Begins offshore