ENI EI-39Eugene Island 39 Decommissioning
Pre-mob · Mobilization Jun 25 · Contract 5010006273
BK

Cost & margin

Internal only · lump-sum — cost-to-date vs budget is the margin
Margin — source of record needed

Three bases exist in the master sheet. Reconcile with Promethean before reporting margin.

Client bid
$11.97M
Internal build
$12.95M
−$981K
Markup
5%
→ ~4.8% GPM
Facilities vs Morrison: −3.06%

Milestone billing & AR

Milestone → evidence → invoice → payment
ScopePriceTarget dateStatus
PM & Engineering$640,964May 22 – Jun 2550% invoiced
Wells P&A$6,066,537Jul 4 – Aug 24Planned
Facilities$5,264,855Aug 26 – Sep 26Planned
Total contract value$11,972,356

Vendors

From Procurement (09)
SubcontractorRoleContract value
Chet Morrison ContractorsVessels / pipeline / heavy-lift$4,997,000
Crescent Energy ServicesWell P&A$2,104,807
Gulf Offshore LogisticsVessels$739,896
C-Dive (Champagne)Diving$230,475
Broussard BrothersDock services$130,805
EcoserveWaste disposal$75,962