ENI EI-39Eugene Island 39 Decommissioning
Pre-mob · Mobilization Jun 25 · Contract 5010006273
BK

Daily reports

Eng & Ops · DPR source: DE25060.xlsx · pre-mob until Jun 25
Daily brief · pre-mobilization

Daily briefs begin at mobilization · Jun 25. Once crews are offshore, draft today's DPR right here — no more spreadsheets.

Draft today's DPR
The DE25060 workbook in 04 Cost Control is the EI-39 DPR/DCR source, but the current daily tabs carry TO-8/BSEE content. EI-39 daily reports begin at mobilization · Jun 25. TO-8 content is intentionally excluded from EI-39 actuals.

POB & field activity

Populates at mobilization
Personnel-on-board, op-code activity, and per-well progress will go live with Report #1 on Jun 25. Pre-mob the only field activity is onshore PM&E.

Scope & assets

5 wells · 3 structures · 2 pipelines · offshore Jun–Oct
Wells
A001
Planned
API 177094126200
P&A: 3d (Jul 10–13)
TA'd, tree removed; cut/pull casing & conductor
A002
Planned
API 177094132600
P&A: 17d (Jul 13–30)
Shut in; fish & sand
A003
Planned
API 177094140500
P&A: 17d (Jul 30–Aug 16)
Shut in; valve locked open; damaged through-tubing
A004
Planned
API 177094142500
P&A: 8d (Aug 16–24)
TA'd, no tubing; assess C-annulus isolation
#2 (002 ST1)
Planned
API 177094126901
P&A: 3d (Jul 1–4)
Fish; production open
Structures
EI-39 A
Planned
Four-pile facility, 5 decks + crane
WD 12 ft
Window: Sep 21–26
EI-39 #2
Planned
Single-well caisson
WD 10 ft
Window: Sep 15–19
EI-39 #4
Planned
Single-well caisson
WD 12 ft
Window: Sep 19–20
Pipelines
PSN 12507
Planned
8", ~1,000 ft, Platform A → SSTI
OUT (assumed hydrocarbon-loaded)
Window: Aug 26–28
PSN 12515
Planned
4", ~5,031 ft, Caisson #2 → A
PABN (flushed 2017)
Window: Aug 25–26